Gateway Newsletter / JUL
SATELLITE IMAGE OF THE AIRPORT SITE
Legend
Passenger Terminal
Sydney Metro Train Station
Airport Business Park/Parking
Aviation Support Facilities
Air Cargo Precinct
1972 linear meters of large pipes and 224 meters of reinforced concrete drainage structures have been laid underground.
520,000 m 2 of spray seal was used to create the terminal site’s surface in preparation for construction.
As of June 2021, we have moved more than 16,000,000 m 2 of earth.
westernsydney.com.au » 15
Made with FlippingBook Digital Publishing Software